RenewTechnologies
  1. Home
  2. Projects
  3. Biogas
  4. Simmer & Jack Landfill

Johannesburg, Gauteng

Simmer & Jack Landfill

Gas chilling for a 2,000 Nm³/h landfill-gas-to-electricity plant in Johannesburg.

Landfill gas
Simmer & Jack Landfill site photograph
2,000Nm³/hChiller capacity
2014Commissioned

The project

Simmer & Jack is a landfill-gas-to-electricity project where the gas fires reciprocating engines. Engines are unforgiving of wet gas, so Renew supplied an APROVIS FriCon chiller sized for the full 2,000 Nm³/h flow.

Dry, cool gas protects the engines, reduces maintenance downtime and improves combustion efficiency.

Project details

LocationJohannesburg, Gauteng
ClientEner-G Systems
Commissioned
CategoryLandfill gas

Infrastructure supplied

  • 1× APROVIS FriCon gas chiller, 2,000 Nm³/h landfill gas