Welgedacht Wastewater Treatment Works

A 2,150 m³ double-membrane gas holder giving the works steady sewage gas for utilisation.

Sewage gasBiogas
Welgedacht Wastewater Treatment Works site photograph
2,150m³Gas storage
2015Commissioned

The project

Digester gas production at a wastewater works never matches demand minute by minute. Welgedacht solved this with a 2,150 m³ Sattler double-membrane gas holder supplied and installed by Renew for WEC Projects.

The holder buffers production peaks, maintains constant delivery pressure to the gas users and keeps losses to a minimum with a permanently gas-tight inner membrane.

Project details

LocationWelgedacht, Gauteng
ClientWEC Projects
Commissioned
CategorySewage gas, Biogas

Infrastructure supplied

  • 1× Sattler double-membrane gas holder, 2,150 m³